Satrio to Brass closed from September 11
VIVAnews -after experiencing delays, finally closing some roads Satrio towards Rasuna Said closed from Sunday, September 11, 2011.
The closure was done yesterday, but since there is a pipe leak at the underpass barriers Casablanca, closure of roads to be postponed. This is a continuation of the closure of the road construction project Kite Non Toll (JLNT)-Malay Kampong Tanah Abang.
"The north side of the Road underpass next to the Embassy of Malaysia to the Rasuna Said Satrio access so closed Sunday," said the head of the operational Directorate of The Bina traffic Polda Metro Jaya Assistant Commissioner Jakarta, Usman Latif on Friday September 9, 2011.
However, Latif appealed the riders didn't have to worry about, because the officer had already set up alternative roads. The vehicle was about to go the way of brass, can pass through the streets of Denpasar North and exit on the side of the tower.
An alternative way in the back of the building that long reach Women Work 300 meters, while the total length of this road reaches 700 meters when connected with seven meters wide. Ascertained one way that can penetrate into the Rasuna Said this could be traversed by two four-wheeled vehicles.
More Latif reveals, originally The Nexus JAWA road closure implemented on request Saturday next. But police wanted to advance socialisation to the community. "Traffic signs-traffic signs and completeness, especially at night to be heeded," he added.
He added, the closure of the north side of this plan in conjunction with the opening of the South side of West Street, Rasuna Said Raya Denpasar towards Satrio. Until now, the it is still closed and heavy equipment still works.
But the opening of the South had to be postponed due to the time of processing is not done yet. "The South access Rasuna Said to Peter Guidi will be opened on September 21, 2011," he said. (umi)
• VIVAnewsThere Is A Pipeline Leak, Satrio Cancel Access Closed
VIVAnews -DKI Jakarta provincial Government was forced to delay the closing of some roads Satrio Rasuna Said, related to the development projects of non toll highways, Kampung Melayu-Tanah Abang.
Deputy Head of the Department of transportation Jakarta, Novizal, explained, at first closing will take place today, Thursday, September 8, 2011. Because there is a pipe leak barriers in Casablanca, the closure of the underpass roads are driven in time.
"Delayed slightly as a result of an event of a leak underpass pipe in Casablanca. The closure will be coordinated first with The Nexus Metro Polda Jaya and JAKARTA, "said Novizal to VIVAnews.com.
Delivered Novizal, the current readiness of the closing of some roads are ready completely. Traffic signs have been installed, and the way such alternative Denpasar Road behind the Embassy of Malaysia, had long been in the get started and can be traversed.
"People do not have to worry, the closure of these roads will not be done unannounced. We will certainly be socialised first, "he asserted.
In addition, Novizal was informed that the closure would be carried out on the two roads at once. As known, until recently the road towards jalan Rasuna Said Satrio still closed and heavy equipment still works.
"While some roads Satrio towards Rasuna Said roads are closed, also still in an otherwise closed, because of the heavy equipment still works. Hopefully not a standstill, because the alternative route prepared, "he said.
Originally planned the closure of roads from Satrio towards Rasuna Said will be done over the past three months. This was done seiringan with the opening on the South side of which is currently closed. Before closing, testing is done, and socialization would be first.
Tomorrow, Satrio Towards Rasuna Said Closed
VIVAnews -Start tomorrow's roads Prof Dr Satrio towards Rasuna Said. Closing this as a continuation of the project construction of Overpass Non Toll (JLNT) Tanahabang-Kampungmelayu.
According to information of public relations Department of transportation Jakarta, which would shut down the road is passing beside the Embassy of Malaysia leads to the Brass. Later, a vehicle who was about to go brass, can pass through the streets of Denpasar North and exit on the side of the tower.
The Head Office of PU Jakarta, Ery book Basworo said the closure for approximately three months it is estimated to be in unison with the opening of the South side of which is currently closed. "Our infrastructure is ready," said Ery book VIVAnews.comwhen contacted Wednesday, September 7, 2011.
He added, before the closing was done, according to the access road, PU JAWA Ery book already do testing and socialization in advance to the community. The road next to the Embassy of Malaysia was only to be closed over 100 meters.
In addition, he continued, it will also coordinate with the Metro Police Department of Transportation Office of Jaya and Jakarta are related to the closure of the road. (eh)
Access Satrio Towards Brass Closed 3 months
VIVAnews -Office of Transportation Jakarta closes roads Prof Dr Satrio towards Rasuna Said starting today. Closing this as a continuation of the project construction of Overpass Non Toll (JLNT) Tanahabang-Kampungmelayu.
According to information of public relations Department of transportation Jakarta, which would shut down the road is passing beside the Embassy of Malaysia leads to the Brass.
The vehicle was about to go the way of brass, can pass through the streets of Denpasar North and exit on the side of the tower.
The Head Office of PU Jakarta, Ery book Basworo said the closure for approximately three months it is estimated to be in unison with the opening of the South side of which is currently closed.
Ery book reveals it has finished making its way towards Jalan Rasuna Said translucent on the Road North of Denpasar.
"We've made it on the road path translucent Denpasar North, 300-metre dibeton already," said Ery book to VIVAnews.com.
He adds, it's just a road that is closed over about 100 yards which side between under pass and turn left towards the brass. "Soon there will be drilled," he added.
Before the closure of access roads, performed by Ery book, The PU JAWA doing trials and socialization in advance to the community.
In addition, continued he, it is also coordinating with the Metro Police Department of Transportation Office of Jaya and Jakarta.
Ery book explains, the alternative road is behind the woman's long reach Building Darma 300 meters, while the total length of this road reaches 700 meters when connected with seven meters wide.
Ascertained one way that can penetrate into the Rasuna Said this could be traversed by two four-wheeled vehicles.
While he acknowledged the closure of the access road on the South side is indeed incompatible with the original plan. Given the many obstacles faced in drilling at that location, one of which contained raw water pipe. "To the South side, a bit out of the promise. Because the utility could not unexpected, "he admits.
The original plan, the opening of the South side of the access is done on 21 July. But until now, work is still ongoing. Before DPU Jakarta also made the closure of the Access Road towards Jalan Sudirman Filework. Currently, access roads were opened and be back crossed by the rider. (eh)
September, Satrio Towards Rasuna Said Closed
VIVAnews -Office of public works DKI Jakarta immediately closes road access Roads towards Satrio Rasuna Said. The closure of this road construction project related Kite Non Toll (JLNT) Tanahabang-Kampungmelayu.
Closure for approximately three months it is estimated to be in unison with the opening of the South side of which is currently closed.
The Head Office of PU Jakarta, Ery book Basworo said his Department is currently making its way towards the middle of the road Rasuna Said translucent on the Road North of Denpasar.
"We are currently working on the road that translucent (Denpasar), now it is dibeton all the 300 metres," said Ery book, in the Office of The PU JAWA, Jatibaru, Central Jakarta, Thursday, August 11, 2011.
He added roadwork translucent, is still not finalized, but the work was estimated to be completed by this weekend. So in early September, the way it can be used. translucent
"There are still about 10 yards longer. Hopefully this week is complete. So the beginning of September is already doable closure, "he said.
Before the closure of access roads, performed by Ery book, The PU JAWA will do a test run and socialization in advance to the community. The road next to the Embassy of Malaysia, his plan would only be closed all the 100s of metres.
In addition, he continued, it will also coordinate with the Metro Police Department of Transportation Office of Jaya and Jakarta are related to the closure of the road.
"The way of alternatives should be completed first. When it's ready we tested, new applied. It also requested the approval of the authority of the traffic, such as Police and Dishub, "as the star.
Ery book explains, the alternative road is behind The woman's long reach Darma 300 meters, while the total length of this road reaches 700 meters when connected with seven meters wide. Ascertained one way that can penetrate into the Rasuna Said this could be crossed by two four-wheeled vehicles.
He acknowledged the closure of the access road on the South side is indeed incompatible with the original plan. Given the many obstacles faced in drilling at that location, one of which contained raw water pipe.
"To the South side, a bit out of the promise. Because the utility could not unexpected, "he admits.
The original plan, the opening of the South side of the access is done on 21 July. But until now, work is still ongoing. Before DPU Jakarta also made the closure of the Access Road towards Jalan Sudirman Filework. Currently, access roads were opened and be back crossed by the rider. (eh)